Page 74 - The Six Sigma Project Planner
P. 74

Duration Estimates
                    Activity   Depends                (b)                 Weighted           18        19
                                            (a)                  (c)              17  Variance    Sigma
                                On                   Most                 Average
                                        Optimistic           Pessimistic
                                                     Likely
                       A                    1          2          3            2.00       0.11      0.33
                       B         A          3          5          9            5.33       1.00      1.00
                       C         B          2          8         14            8.00       4.00      2.00
                       D         C          1          6         13            6.33       4.00      2.00

                       E         B          1          3          7            3.33       1.00      1.00
                       F         E          3          4          8            4.50       0.69      0.83
                       G        D, F        2          6         11            6.17       2.25      1.50

                    The network chart for this project is shown below. The critical path (using the most
                    likely duration estimates) is indicated as a solid line.


                                                             C          D

                                        A          B                               G


                                                              E         F


                    There are several ways in which this information can be analyzed. For example, we
                    could compare the schedules that result from assuming that a given set of durations is
                    correct. The results of this analysis are presented in the table below. This analysis
                    provides best-case, expected, and worst-case scenarios. For the example, the project is
                    scheduled to begin on March 31, 2003. The best-case finish would be April 11, 2003. The
                    two expected finishes are May 7 (based on the weighted averages) or May 6 (using the
                    most likely duration estimates). The worst-case finish would be June 6. These estimates
                    can be compared to the project’s target due date and used for planning. The optimistic
                                                                  20
                    analysis can be used in crash schedule planning  or the pessimistic analysis can be used
                    for evaluating the effect of shifting resources to higher-priority projects.




                    17
                      Weighted average = (a + 4b + c) / 6.
                    18                 2
                      Variance = [(c - a) / 6] .
                    19
                      Sigma = [(c - a) / 6].
                    20
                      See “Calculating the Cost of a Schedule,” p. 66.


                                                             57
   69   70   71   72   73   74   75   76   77   78   79