Page 75 - The Six Sigma Project Planner
P. 75
Weighted Average Schedule Most Likely Schedule
Task Duration Start End Task Duration Start End
A 2d Mon 3/31/03 Tue 4/1/03 A 2d Mon 3/31/03 Tue 4/1/03
B 5.33d Wed 4/2/03 Wed 4/9/03 B 5d Wed 4/2/03 Tue 4/8/03
C 8d Wed 4/9/03 Mon 4/21/03 C 8d Wed 4/9/03 Fri 4/18/03
D 6.33d Mon 4/21/03 Tue 4/29/03 D 6d Mon 4/21/03 Mon 4/28/03
E 3.33d Wed 4/9/03 Mon 4/14/03 E 3d Wed 4/9/03 Fri 4/11/03
F 4.5d Mon 4/14/03 Mon 4/21/03 F 4d Mon 4/14/03 Thu 4/17/03
G 6.17d Tue 4/29/03 Wed 5/7/03 G 6d Tue 4/29/03 Tue 5/6/03
Optimistic Schedule Pessimistic Schedule
Task Duration Start End Task Duration Start End
A 1d Mon 3/31/03 Mon 3/31/03 A 3d Mon 3/31/03 Wed 4/2/03
B 3d Tue 4/1/03 Thu 4/3/03 B 9d Thu 4/3/03 Tue 4/15/03
C 2d Fri 4/4/03 Mon 4/7/03 C 14d Wed 4/16/03 Mon 5/5/03
D 1d Tue 4/8/03 Tue 4/8/03 D 13d Tue 5/6/03 Thu 5/22/03
E 1d Fri 4/4/03 Fri 4/4/03 E 7d Wed 4/16/03 Thu 4/24/03
F 3d Mon 4/7/03 Wed 4/9/03 F 8d Fri 4/25/03 Tue 5/6/03
G 2d Thu 4/10/03 Fri 4/11/03 G 11d Fri 5/23/03 Fri 6/6/03
58