Page 75 - The Six Sigma Project Planner
P. 75

Weighted Average Schedule                 Most Likely Schedule
                          Task  Duration  Start     End         Task Duration Start       End
                          A     2d        Mon 3/31/03   Tue 4/1/03   A   2d     Mon 3/31/03   Tue 4/1/03
                          B     5.33d     Wed 4/2/03   Wed 4/9/03   B   5d      Wed 4/2/03   Tue 4/8/03
                          C     8d        Wed 4/9/03   Mon 4/21/03   C   8d     Wed 4/9/03   Fri 4/18/03
                          D     6.33d     Mon 4/21/03   Tue 4/29/03   D   6d    Mon 4/21/03   Mon 4/28/03
                          E     3.33d     Wed 4/9/03   Mon 4/14/03   E   3d     Wed 4/9/03   Fri 4/11/03
                          F     4.5d      Mon 4/14/03   Mon 4/21/03   F   4d    Mon 4/14/03   Thu 4/17/03
                          G     6.17d     Tue 4/29/03   Wed 5/7/03   G   6d     Tue 4/29/03   Tue 5/6/03

                                 Optimistic Schedule                   Pessimistic Schedule
                          Task  Duration  Start     End         Task Duration Start        End
                          A     1d        Mon 3/31/03   Mon 3/31/03   A   3d    Mon 3/31/03   Wed 4/2/03
                          B     3d        Tue 4/1/03   Thu 4/3/03   B   9d      Thu 4/3/03   Tue 4/15/03
                          C     2d        Fri 4/4/03   Mon 4/7/03   C   14d     Wed 4/16/03   Mon 5/5/03
                          D     1d        Tue 4/8/03   Tue 4/8/03   D   13d     Tue 5/6/03   Thu 5/22/03
                          E     1d        Fri 4/4/03   Fri 4/4/03   E   7d      Wed 4/16/03   Thu 4/24/03
                          F     3d        Mon 4/7/03   Wed 4/9/03   F   8d      Fri 4/25/03   Tue 5/6/03
                          G     2d        Thu 4/10/03   Fri 4/11/03   G   11d   Fri 5/23/03   Fri 6/6/03