Page 79 - The Six Sigma Project Planner
P. 79

Worksheet 25. Statistical Analysis of Project Duration


                                                                                Lower 95%     Upper 95%
                        Path          Mean         Variance        Sigma
                                                                                 Estimate      Estimate


















                               Project Due Date

                               Expected Project Completion Date

                               Standard Deviation of Project Completion

                               95% Lower Confidence Interval (expected
                               completion date minus two standard deviations)
                               95% Upper Confidence Interval (expected
                               completion date plus two standard deviations)
                               Probability of Meeting Due Date

                    If the probability of not meeting the due date is high, the deadline should be discussed
                    with the project sponsor. In some cases it is necessary to modify the project’s charter,
                    assign additional resources, etc.

                    Using Simulation to Analyze Project Schedules
                    The analysis conducted above involves a number of simplifying assumptions and
                    approximations. In most cases, the accuracy of the results will be more than adequate.
                    However, it is possible to conduct a more precise analysis using computer simulation.
                                                                  ®
                                                                        22
                    The example here uses the program Crystal Ball  (CB).

                    22
                      Available from Decisioneering, Inc., www.decisioneering.com.

                                                             62
   74   75   76   77   78   79   80   81   82   83   84