Page 149 - The Toyota Way Fieldbook
P. 149

126                       THE TOYOTA WAY FIELDBOOK


        Standardized Work Documents

        There are three primary documents used for developing standardized work,
        and many other related or supporting documents. It is not the purpose of this
        book to go in to detail on how to use each of these tools but it is worth saying a
        bit about each of the following:
           1. Standardized Work Chart
           2. Standardized Work Combination Table
           3. Production Capacity Sheet

        Standardized Work Chart
        Originally the document that Toyota used for the Standardized Work Chart was
        primarily a diagram of the work area and worker flow. There was no verbal
        description of the work method and no element times associated with each step.
        The detailed element times were a separate document, such as the Standardized
        Work Combination Table. Somewhere along the line  in many operations the
        Standardized Work Chart and the Standardized Work Combination Table were
        blended into one simplified document that is often referred to (outside of Toyota
        at least) as a “Standardized Work Sheet,” or “Standardized Work Chart.”
            The Standardized Work Sheet is used initially as a tool to identify and elimi-
        nate waste. After improvements are made, the new method becomes the baseline
        for improvement. Then it is posted in the work area as a method of visual con-
        trol for management to verify adherence to the standard.
            As with any tool, its use is dependent upon the circumstances. What is the skill
        of the user? What condition is being corrected? Do not worry about trying to
        achieve a perfect result or using the sheet “correctly.” During the initial appli-
        cation of standardized work in a process, the first step is to create a baseline for
        improvement. The steps of the process are:

           1. Record the sequence of the job (the work steps)
           2. Diagram the work movement.
           3. Identify waste
           4. Determine improvements needed to achieve desired results (meeting the
              takt time is an objective that is explained below)
           5. Incorporate material usage and flow (standard in-process stock)
           6. Document improved method
            Figure 6-5, below, provides an example of a Standardized Work Sheet. The
        main elements are the work sequence and the diagram of the work movement.
        Once the steps and diagram of the work flow are completed we ask the question,
        “What do you see?” Look at the diagram and describe your initial impression.
   144   145   146   147   148   149   150   151   152   153   154