Standardized Work/IPCS Audit Form
             IPCS:  Y / N Are all of the assigned tasks being performed by this operator?  If no, why?  Y / N Is this operator performing checks not identified on the IPCS? If yes, are these checks necessary? Why?  Y / N Should additional checks be added to the IPCS?  If yes, what are they?  Y / N Should any checks be moved from this IPCS to another operator’s I
                    Y / N  Y / N  Y / N  Y / N  Y / N  Y / N  Y / N  Y / N  Y / N  Y / N  Y / N  Y / N  Y / N  Y / N  Y / N
                                                                             03/12/01  DPS Office



          Standardized Work/IPCS Audit Form  Does the number of Standardized Work Charts in the cell match the number of operators?  Is the number or SWIP currently in process correct? (No batching, no gaps, etc.)  Are the times correct for each operational step? (Attach time study of at least 5 consecutive cycles)  Do the Donnelly Critical and Donnelly Safety i
             Auditor
               Date















               of     Are the charts posted within the cell? Is the takt time on each chart correct? Is the work cell running to takt time? Are the 3 elements of Standardized Work represented on the chart? If no, which elements are missing? Is the number of SWIP shown on the chart correct?  Is the work sequence shown on the chart correct? If no, what should be c


             Workcell:  Operation #  General:  Specific Operation:  If no, why?  If no, why?  Figure 20-4.