Page 95 - The Toyota Way Fieldbook
P. 95

72                        THE TOYOTA WAY FIELDBOOK


              dramatically reduce this time.  Also known as “quick changeover,” or
              “rapid changeover,” this method can be applied any time equipment is
              “changed” from one physical state to another. This may include tool
              changes, material changes, or changing to a different product or configu-
              ration. Additional causes for out-of-cycle losses are easily identified
              using a simple comparison of value-adding and non-value-adding activ-
              ities as shown in the following case example.



                Case Example: Improving Operational Availability at
                the Cedar Works
                The Cedar Works produces wood birdhouses. The first step of the
                operation involves slicing the raw wood stock into thin slabs using a
                band saw. As a result of a sharp increase in demand, this operation was
                running seven days a week, 24 hours a day, in an attempt to maintain
                production levels. After four hours of standing in the circle, it was
                estimated, however, that only about 30 percent of the saw capacity
                was being utlilized. The department manager, was incredulous. “That’s
                crazy!” he said. “We’re working 24/7! How can we get more out of this
                operation?” Having not had the opportunity to stand in the circle, he’d
                fallen into the trap of confusing “work” and “activity” with value-adding
                time, confusing the activities of the person and the machine.

                To improve his understanding, we first reviewed the concept of the
                seven forms of waste (non-value-adding) and value-adding activities.
                Beginning with the easier side of the comparison, we identified the value-
                adding activity and agreed that the saw added value when the blade
                was cutting wood. We also agreed that there are other “necessary”
                activities performed, though they do not help achieve the end goal of
                cutting more wood. We then agreed that only when the blade is cutting
                wood is value truly added by the saw. Now the comparison was simple:
                On the value-added side we had “blade cuts wood,” and on the non-
                value-added side, “everything else.”
                By standing in the circle and observing, we saw many situations when
                the blade was not cutting wood. This list was shared with the operators,
                who were asked to add any additional items that were not observed.
                We suggest standing in the circle at various times of the day and on
                multiple days to get a fairly complete understanding of the situation.

                Figure 4-7 shows a side-by-side comparison of value-added and non-
                value-added activities.  It shows a typical situation for any operation.
                There will generally be few items on the value-added side and many on
                the non-value-added side. This provides a large selection to capture
   90   91   92   93   94   95   96   97   98   99   100