Page 310 - Trenchless Technology Piping Installation and Inspection
P. 310

274    Cha pte r  S i x

          10 hours, strength would be appropriate, in combination with antici-
          pated values of f  and f  during this period. For the postinstallation
                        o     R
          phase, a 1000-hour collapse strength is conveniently assumed as which
          time the soil has locally redistributed itself around the pipe to provide
          some lateral constraint against collapse, in combination with the rela-
          tively tight clearance between the replacement pipe and the expanded
          borehole walls, characteristic of a pipe-bursting operation. For this
          postinstallation phase, the tension reduction factor, f , is equal to 1.0.
                                                     R
             Based on the ovality reduction factor, dependency trend provided
          in ASTM F1962, and consistent with the present simplified approach,
          it is reasonable to assume a maximum overall value of f  of approxi-
                                                         o
          mately 0.5 to account for ring deformation due to initial ovality plus
          that induced by postinstallation loadings.
             The greater short-term (or 10-hour) collapse strength relative to
          that at 1000 hours would tend to be offset somewhat by the tension
          reduction factor, f , during installation, as well as the degradation at
                         R
          possible elevated temperature as the HDPE pipe sits on the surface
          prior to installation. However, the latter effects would not be experi-
          enced simultaneously, as the pipe is placed at its maximum depth
          and distance. Therefore, the 1000-hour (postinstallation) collapse
          characteristics, as adjusted for the above soil density and ovality con-
          siderations, are conveniently employed to evaluate the vulnerability
          to collapse. Based upon the above discussion, the following planning
          guide is determined:
                H  (ft) = 1000 hour water head × f × f /γ
                 all                         o  R
                      = 1000 hour water head × (0.5) × (1.0)/(2.0)

             or,

                H  (ft) = 1000 hour water head/4.0              (6.7)
                 all
          where H  is the allowable (maximum) pipe depth.
                 all
             An additional degree of margin (safety factor) may exist due to
          soil arching effects, reducing the effective load on the pipe), as well as
          the aforementioned degree of lateral constraint of the pipe provided
          within the cavity.
             As an example, consider the feasibility of installing a 4-in. DR 17
          pipe at a depth of 12 ft. Applying Eq. (6.7) results in

                      H  (ft) = 1000 hour water head/4.0
                        all
                             = 62 ft/4.0
                             = 15.5 ft

             Thus, the present planning guide indicates that the proposed 12-ft
          depth is reasonable.
   305   306   307   308   309   310   311   312   313   314   315