Monetary
                Repair
                  Accepted Tolerance Penalties Repair Types Requirements  No deduction,  Removal of wrinkles  Repair if exceeding  Generally  assuming adequate  (fins) and coat area  5 percent of  5 percent of   thickness is  with approved epoxy  nominal diameter  nominal diameter   achieved. material. Trim to  of existing pip











                  Probable Cause  Undersized or   deteriorated localized  section of existing pipe.  The corrugated   pipe may have been  measured incorrectly  at the inside diameter   or high point of the   corrugations, rather  than the center of the   corrugations.











                  Defects  Wrinkles/fins/  folds (LW)/(LF)