Page 252 - Uninterruptible Power Supplies
P. 252

Some System Failures: The Light of Experience!
            250   Chapter Ten


            the system interpreted as a battery failure. Sufficient warning was
            given to ensure that the fire did not spread from the battery room.
            Needless to say, the entire computer network was shut down.
              The resulting investigation established that the three parallel
            strings of 400-V 400-Ah flooded lead acid cells had not been properly
            maintained. Maintenance logs only recorded that the cells had merely
            had electrolyte levels topped up. There was no record of torque testing
            the cell terminals. It was found that the terminals on some cells were
            only finger tight! The heating and cooling caused by the discharge
            cycles had caused further deterioration of the already bad connections
            and eventually arcing had occurred, initiating a serious fire.
              This incident indicates the importance of proper battery mainte-
            nance. Before passing on to the next incident, spare a thought for the
            individual who had to enter that battery room to disconnect the system!


            An Unsuccessful Attempt at Cost Reduction
            A project engineer had to design a system comprising a static UPS, a
            generating set, and the usual ancillary equipment to complete the
            installation. After the system had been installed it was found that the
            generating set was unable to support the load in bypass mode.
              In unraveling the problem it was discovered that the project engineer
            had approached several suppliers for a complete installation and had
            chosen a particular supplier, only to be told by his management that
            the cost was too high. As a result he decided to design the system him-
            self, but with insufficient knowledge of the component parts. The load
            included a large number of office-type PCs with a high harmonic con-
            tent and a high crest factor, measured at the generator as 3:1. The gen-
            erator and its voltage regulator had been chosen without reference to
            the harmonic loading.
              This failure indicates the hazards of not employing a main contractor
            with responsibility for coordinating all aspects of the installation. An
            experienced contractor, before accepting responsibility, would undoubt-
            edly have asked questions about the load and its harmonic content.


            Empty Sumps
            Exporting generating sets to developing countries can lead to interest-
            ing problems! Two sets were shipped for a computer center and
            installed by local staff. On commissioning, both sets failed due to there
            being no lubricating oil in the sumps. Generating sets are shipped with
            drained sumps, and the need to add oil had been overlooked.






         Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)
                    Copyright © 2004 The McGraw-Hill Companies. All rights reserved.
                      Any use is subject to the Terms of Use as given at the website.
   247   248   249   250   251   252   253   254