132 Chapter Six
Exhibit 6-15
Plan of hoist platform runaway.
1
4
2
3
2
5
1
Building
1. Rack and Pinion Hoists
2. Common Mast
3. Common Platform
4. Runaway to Building
5. Tie Backs and Supports
in the building or for ground logistics reasons. In addition, sometimes a common plat-
form is utilized to allow several hoist assemblies to access one large platform struc-
ture adjacent to the building, thus allowing for more than two hoists in one location,
if required.
The hoist noted can accommodate as many as 40 people and can carry loads of up to
8000 pounds. In a hoist designed for carrying people, the operator typically rides in the
car, but in a machine that is not intended for personnel, this is not permitted. The car