Page 179 - Urban Construction Project Management
P. 179

134    Chapter Six
         Exhibit 6-16
                              Item                                                        Included
         Checklist for
         hoists.               1. Construction personnel hoists
                               2. Construction material hoists
                               3. Combination personnel/material hoists
                               4. Location of hoist—internal or external to building
                               5. Loading dock for hoists
                               6. Barricades for hoists and loading dock
                               7. Signage
                               8. Flashing yellow caution lights
                               9. Concrete foundation pad for hoist
                              10. Tie backs of hoist to the structure
                              11. Runaways from hoist tower to building
                              12. Power for hoists
                              13. Power for lighting and outlets at hoist landings
                                 and loading dock
                              14. Permits
                              15. Engineering
                              16. Sidewalk closing
                              17. Lane closing
                              18. Direction of the flow of traffic
                              19. Bus lanes and stops
                              20. Subway entrances and exits
                              21. Access to fire hydrants
                              22. Visibility of traffic signage or relocation of same
                              23. Zone of influence of the hoist for sidewalk bridge
                              24. Sidewalk Bridge for pedestrian protection
                              25. Lighting under sidewalk bridge
                              26. Anchorage of sidewalk bridge
                              27. Weather-resistant enclosure at hoist entrance
                                 to building
                              28. Ramps from hoist entrance into building
                              29. Coordination of hoist location with permanent
                                 building facilities
                              30. Schedule for the availability of permanent
                                 service and passenger elevators
                              31. Use of hoists for construction of tenant fit up
                                 program
                              32. Structural support for the hoist pad, hoist
                                 tiebacks, sidewalk bridge, and sheds
                              33. Structural reinforcing for the hoist area
                                 loading dock
   174   175   176   177   178   179   180   181   182   183   184