140    Chapter Six
        FIELD OFFICES AND SHANTIES



                            As part of the site logistics planning, it is important to identify the location for the
                            CM/GC field office, and those of the subcontractors. See Exhibit 6-21 for the field
                            office checklist. Initially during the demolition and then the excavation and foundation
                            phase of the project, construction field offices are often housed in self-contained trail-
                            ers that can be rented. The trailers can be located on the site, if open space is available.
                            Often they are located adjacent to the site (see Exhibit 6-22 and Exhibit 6-23), or on top
                            of the sidewalk bridge surrounding the construction site. If the trailers are to be located
                            on top of the sidewalk bridge, then a heavy load bridge (300lbs/sq.ft.) to allow for the
                            installation of the trailers is required.

                            The field offices and shanties are often then incorporated within the space inside the con-
                            struction of the building, once the building structure is in place. Locations that should be
                            considered are: (1) first floor retail space, (2) garage parking area, (3) below grade stor-
                            age space, and (4) large contiguous space within the lower floors of the building. The



         Exhibit 6-21
                              Item                                                        Included
         CM/GC’s field
         office and shanties   1. CM’s field office
         checklist.            2. Subcontractor’s field office and shanties
                               3. Subcontractor storage of materials
                               4. Fire resistant construction
                               5. Sprinkler protection of shanty areas
                               6. Emergency evacuation of construction
                                 personnel
                               7. Power for field offices and shanties
                               8. Location of temporary bathrooms
                               9. Heaters and A/C for construction shanties
                              10. Required shanties for Local 14, Teamster,
                                 and Master Mechanic
                              11. Telephone, fax, Internet service for CM
                                 and trades
                              12. Security of site and offices
                              13. Storage of flammable and hazardous
                                 materials
                              14. Location of office and shanties relative
                                 to site entrance
                              15. Guard booth to control site access
                              16. Fire extinguishers
                              17. Types of interim heaters, air conditioners
                                 and fire protection
                              18. Emergency contact information
                              19. Communication system on the site