142    Chapter Six
                            location is ideally in walking distance from the personnel construction entrance to the
                            site, and logistically in the middle of the action. The PM should try to avoid having to
                            take an elevator or hoist to get to the CM/GC’s field office if possible to maintain con-
                            trol of the site and overall security.

                            Field offices and shanties should be built out of fire retardant materials to minimize
                            potential fire damage and comply with the local building codes, especially when the
                            building is ready for a temporary certificate of occupancy (TCO). At this point in the
                            project, all field offices and shanty spaces may have to be fully sprinkled, if required
                            by code. The installation of a permanent sprinkler loop (if required by local codes) with
                            temporary upright heads is often utilized to provide coverage of these temporary struc-
                            tures. As work progresses within the structure, the location of the shanties may have to
                            change. Exhibit 6-24 shows a phasing plan for the relocation of shanties.





         Exhibit 6-24                                                T.O. Building
                                           Electrical shanty            FL 34
         Staging for
                                                (12'×12')              FL 33
         shanties.                        Mechanical shanty            FL 32  Phase 4
                                                                              Shanties serve floors 30–34
                                                (12'×12')
                                                                       FL 31  Completion of phase 4
                                           Plumbing shanty
                                 Tower          (12'×12')
                                                                       FL 30
                                                                       FL 29
                                                                       FL 28B
                                           Electrical shanty           FL 28A  Phase 3
                                                (12'×12')              FL 28  Shanties serve floors 25–29
                                          Mechanical shanty  Mechanical Floor
                                                (12'×12')  Transfer Level  FL 27  Completion of phase 3
                                           Plumbing shanty             FL 26  Shanties move to 30th floor
                                                (12'×12')
                                                                       FL 25
                                                                       FL 24
                                                                       FL 23
                                                                       FL 22
                                           Electrical shanty                  Phase 2
                                                (12'×12')                     Shanties serve floors 18–23
                                          Mechanical shanty            FL 21  Completion of phase 2
                                                (12'×12')              FL 20  Shanties move to 25th floor
                                           Plumbing shanty             FL 19
                                                (12'×12')              FL 18
                                                                       FL 17
                                                                       FL 16
                                           Electrical shanty           FL 15  Phase 1
                                                (12'×12')              FL 14  Shanties serve floors 10–17
                                          Mechanical shanty            FL 13  (including lobby and mezzanine)
                                                (12'×12')              FL 12  Completion of phase 1
                                           Plumbing shanty             FL 11  Shanties move to 9th floor
                                                (12'×12')
                                                                       FL 10
                             Base building
                                Ground
                              floor/street
                             Basement
                               levels
                              SAFETY NET STAGES