Page 198 - Urban Construction Project Management
P. 198

Logistics  153
          schedule. In some cases, a balance may have to be made between the cost to stabilize
          the existing structures and the proposed schedule. Several underpinning and sheeting
          methods can be used to stabilize adjacent buildings and the surrounding soil of the new
          building’s excavation. In addition, a surveyor should be retained to monitor the condi-
          tion of the existing building to make sure no movement is occurring.

          Underpinning

          Jet grouting—A series of pipes are run in the ground under the footings of the existing
          buildings. Grout under high velocity is then sent through the pipes. The grout breaks up
          the soil structure and creates a solid grout–soil mass under the footings. Work could then
          continue with the excavation of the new building.
          Freezing of the soil—A closed pipe system surrounds the footings and refrigerant then
          runs through the pipes. The soil then becomes frozen under the existing footings and
          the new excavation work could continue. In addition, this may be a temporary method
          until a more permanent underpinning method is employed as will be described further.
          This method can also be used to temporarily stop water flow that may be affecting the
          site construction.

          Minipiles—Small diameter (4 to 10 in.) piles are driven through the foundation of the
          existing building (and the new building’s partly excavated area). These piles can be
          made of steel, steel pipe (filled with concrete), or concrete and would then be driven
          into the soil surrounding the existing footings. If vibration is a problem, then pre-bored
          concrete or pipe piles would be placed in the ground and then grouted in place. The
          minipiles could be used as end bearing or friction piles (if sufficient pile surface area
          can develop the required frictional stresses). See Exhibit 6-32 for a typical minipile
          installation.
          Straddling footings with needle beams—New footings can be installed on either side of
          the existing footings. Then steel beams (called needle beams) would be pushed through
          the soil to be supported by the new footings. The needle beams would then support the
          old footing.

          Wall replacement—Walls can be replaced or extended by digging under the existing
          wall and placing a new wall footing foundation. This would be accomplished by remov-
          ing small sections of the wall (to be confirmed by the engineer) and then placing new
          walls on top of the newly created wall footing. See Exhibit 6-34A for details on wall
          replacement methods.

          Prior to starting any work, the checklist shown in Exhibit 6-33 should be reviewed.

          Shoring and Sheeting

          Soldier beams and lagging—Steel H piles are driven into the soil to a depth below the
          excavation level. As the earth is removed for excavation, wooden slots (lagging) are
          placed between the H piles (see Exhibit 6-34). Depending on the stability of the soil, it
          may also be necessary to anchor the H piles. This is accomplished by placing rods (or
   193   194   195   196   197   198   199   200   201   202   203