         Exhibit 6-32                      Existing Building
         Minipiles detail.













                                                                         Needle beam








                                                                         Column

                                                                         Footing or pile cap




                                                                         Minipiles









         Exhibit 6-33
                               1. Obtain drawings of the existing building’s foundation plan.
         Underpinning and      2. If required, dig small test pits around the foundation without disturbing the
         shoring checklist.      structure.
                               3. Prepare a plan of the new excavation and foundation in relationship to the
                                 existing building’s foundation.
                               4. Show a section at the elevation of the new foundations in relation to the old
                                 foundation and the distance between the two. This has to be accomplished at
                                 all impacted foundation locations.
                               5. Indicate the type of existing foundation (spread footing, piles, mat, etc.).
                               6. Indicate the material of the existing foundation (stone, concrete, steel).
                               7. Indicate type of soil or rock encountered under the old foundation.
                               8. Determine estimated load on the existing foundation.
                               9. Locate any water and determine the elevation.
                              10. Review all information with the soils engineer and underpinning specialty
                                 contractor.