Drawings and Specifications  187
          SUMMARY



          • When the drawings and specifications are submitted to the PM, he or she should
            make sure all construction documents have been provided. A log of all the documents
            must be requested from the design team. This will show the list of drawings, speci-
            fications, addendums, bulletins, sketches, all with the latest revision dates.
          • Time must be set aside by the PM so that sufficient effort is devoted to this process
            of document review.
          • The PM must check all the construction documents on a page-by-page basis to eval-
            uate the constructability of the project.
          • A list of long lead items has to be prepared so those items that may fall outside the
            initial schedule can be ordered early.
          • The construction document review will also assist in a value engineering analysis that
            may be required during the document preparation phase of the project.
          • The owner must be made immediately aware of any problems found with the con-
            struction documents review.
          • Coordination of all the design team drawings must be accomplished by the PM to
            avoid conflicts.
          • Access for maintaining equipment, pipes, etc. must be established by the PM.