Drawings and Specifications  183
             • Escalators
             • Generators and fuel tanks
             • Switch gear
             • Batteries
             • Pumps
             • Vaults
             • Cooling towers
             • Chillers
             • Chilled and condenser water pipes
             • Water tanks
             • Thrust loads on pipes
             • Ice storage for mechanical systems
             • Roof gardens
             • Curtain wall supports
          13. Review roof plan
             • Proper penetrations and protection?
             • Adequate slope provided for drainage?
             • Expansion joints required?
             • Overflow scuppers indicated?
             • Drains indicated in the proper location and are there sufficient number of drains?
             • Lightning protection provided and grounding shown?
             • Safety lights located and electrical circuits provided?
             • Mechanical equipment penetrations and flashing indicated?
             • Walkways in the proper locations?
             • Hatches for roof access shown?
             • Proper flashing details?
             • Sufficient clearances as required for maintenance?
             • Communication dishes shown with proper penetration details?
          14. Consistency
             • Toilets line up?
             • Bus ducts (electrical risers) in the proper risers?
             • Equipment rooms indicated?
             • Communications closet indicated?
             • Any offsets?
             • Core plans consistent?
             • All pipes (storm, chilled water, condenser water, sanitary, domestic water, vents)
               in their proper chases?
             • Ducts in proper chases?