Page 228 - Urban Construction Project Management
P. 228
Drawings and Specifications 183
• Escalators
• Generators and fuel tanks
• Switch gear
• Batteries
• Pumps
• Vaults
• Cooling towers
• Chillers
• Chilled and condenser water pipes
• Water tanks
• Thrust loads on pipes
• Ice storage for mechanical systems
• Roof gardens
• Curtain wall supports
13. Review roof plan
• Proper penetrations and protection?
• Adequate slope provided for drainage?
• Expansion joints required?
• Overflow scuppers indicated?
• Drains indicated in the proper location and are there sufficient number of drains?
• Lightning protection provided and grounding shown?
• Safety lights located and electrical circuits provided?
• Mechanical equipment penetrations and flashing indicated?
• Walkways in the proper locations?
• Hatches for roof access shown?
• Proper flashing details?
• Sufficient clearances as required for maintenance?
• Communication dishes shown with proper penetration details?
14. Consistency
• Toilets line up?
• Bus ducts (electrical risers) in the proper risers?
• Equipment rooms indicated?
• Communications closet indicated?
• Any offsets?
• Core plans consistent?
• All pipes (storm, chilled water, condenser water, sanitary, domestic water, vents)
in their proper chases?
• Ducts in proper chases?