Page 111 - Water and wastewater engineering
P. 111

3-8   WATER AND WASTEWATER ENGINEERING

                            alternative access to water when drought conditions lower the water level below the lowest intake
                            port.
                                 While a reservoir or lake will have suspended matter during high wind events, it will seldom
                            have the quantity or quality of the grit produced during flood events on rivers. The river intake
                            structure must be designed to protect the pumps and valves in the transmission system from
                            undue wear from grit.


                              Conduits
                             The intake conduit connects the inlet works with the low-lift pump station. Either a tunnel or a
                            pipeline may be used. Although tunnels have a high degree of reliability, they are expensive to
                            construct. For large water systems, they may be the more economical choice when both capital
                            and long-term maintenance costs are considered.



                              3-3   DESIGN CRITERIA
                               Design Capacity
                             The design process to select a design flow rate ( Q ) is based on a forecast demand. With  Q,  the
                            hydraulics of the intake structure design are based on the worst case estimate of friction loss,
                            an estimate of potential sand intrusion into the conduit, the all-time historic low water level,
                            and a life expectancy of 60    years. Some hydraulic design capacities are listed in  Table 3-3 .
                            Because the life expectancy is very long, prudent engineers use the ultimate flow to design the
                            hydraulic structures (intake tower or crib, conduit, gates, etc.). The design flow is used to select
                            pumps and motors. Space is provided for additional pumps that will be required to meet the
                            ultimate flow.


                                   Layout
                             Division of the intake system into two or more independent cellular or parallel components is
                            recommended for all but the smallest systems. This enhances reliability, provides flexibility in
                            operation, and simplifies maintenance. The  operating deck  (also called the  operating floor  and
                              pump station floor ) that houses the motors, control systems, and so on should be located 1.5 m or
                            more, depending on the maximum wave height, above the high water level of a lake or reservoir
                            or the 500-year flood level of a river supply. The area of the operating deck should be sufficient
                            to allow for the installation and servicing of the pumps, intake gates, and screens. Overhead
                            cranes are an essential feature (Foellmi, 2005; Kawamura, 2000).


                            TABLE 3-3
                             Hydraulic criteria
                            Flow criteria    Capacity           Remarks

                            Design flow      Q                  Capacity at design life under worst case conditions
                            Minimum flow     0.10 Q to 0.20 Q   System specific
                            Ultimate flow    2.0 Q or higher    At life expectancy
                            Adapted from Foellmi, 2005.
   106   107   108   109   110   111   112   113   114   115   116