96                                 Well Control for Completions and Interventions


          requirements differ significantly. In addition, the sequence of events during
          a completion or workover is very different when using a horizontal tree.
             As described, a conventional (vertical) Christmas tree has the valves
          controlling flow arranged vertically through the bore of the tree. A con-
          cept that will be very familiar with anyone working on wells (Fig. 3.8).
             During the construction of a well with a vertical tree a typical sequence of
          events might be:
          •  Drill to TD.
          •  Run and cement liner.
          •  Clean out wellbore.
          •  Run and land completion. When the completion is landed the tubing
             hanger rests inside the uppermost spool in the wellhead—the tubing
             hanger spool.
          •  Install mechanical barriers in the well.
          •  Nipple down (remove) drilling BOP.
          •  Install and test Christmas tree.
          •  Remove mechanical barriers.


































          Figure 3.8 Simplified schematic of a conventional Christmas tree with the valves
          arranged vertically.