Page 342 - Fluid Power Engineering
P. 342

302   Chapter Fourteen




                                 Construction
                  Development        &
                                                     Operation
                    18 to 36      Installation        20 years
                    months         3 to 12
                                   months


              FIGURE 14-1 Three phases of wind project.
                    measurement,windassessment,projectsiting,permitting,en-
                    gineering, financing, engineering procurement, and construc-
                    tion (EPC) contracting, up to preconstruction. The duration
                    of this phase is anywhere from 18 to 36 months. The longest
                    lead-time item is wind measurement; most financiers require
                    at least 2 years of onsite measurement for large projects.
                  2. Construction and installation. In this phase, all the physical on-
                    site activities occur starting from site preparation, turbine
                    transportation, foundation construction, turbine erection,
                    collectionsystemandsubstationinstallation,andprojectcom-
                    missioning. The duration of this phase is 3–12 months, de-
                    pending on the size of the project.
                  3. Operation. In this phase, energy is produced by the wind
                    project. Activities in this phase include, wind plant monitor-
                    ing, and scheduled and unscheduled maintenance.

              Development
              The development phase may be decomposed into the following five
              stages:
                    Prospecting

                    Wind measurement and detailed wind assessment

                    Project siting, PPA, and interconnection

                    Project engineering and procurement

                    Project financing

                 As shown in Fig. 14-2, the stages may have significant time over-
              lap.










              FIGURE 14-2 Typical timeline for the development phase.
   337   338   339   340   341   342   343   344   345   346   347