Page 349 - Fluid Power Engineering
P. 349

Planning and Execution of W ind Projects     309


                      Access roads are permanent infrastructure that must be

                      between 16 and 20 ft wide, 150-ft inside turn radius with
                      load-carrying capacity of 250,000 lb or more, and single axle
                      load of 15 tons per axle for concrete trucks and 10 tons per
                      axle for transporters.
                      The turbine erection pads must be able to withstand loads

                      of 6000 pounds per square foot during lifting of nacelle,
                      rotor, and tower sections. In most large projects, a 500- to
                      600-ton crane is deployed.
                      Crane walk area is a temporary path adjacent to the access

                      road for the crane to move between two turbine locations.
                      This path must be 32–36 ft wide with minimal slope and
                      minimal dip/crest to ensure that a 300-ft crane with high
                      center of gravity can use to travel between sites.

              Foundation Design
              Foundation design is described in Chapter 9. This task is typically
              performed by a foundation design consultant.
              Electrical Design
              Electrical design involves design of the collection systems, substation,
              and interconnection to the grid. Design of collection systems require
              soil thermal resistivity testing along the path of the buried cables. With
              this information, the correct size cables are chosen. Other items in the
              collection system are the protection system and grounding system.
              The protection system is a collection of switchgear (fuses and circuit
              breakers) that protect equipment from fault current (sharp rise in cur-
              rent because of short circuit) by isolating the area with the fault. It
              also allows isolation of parts of a circuit for the purpose of conducting
              repair and maintenance. Utility will review and approve the protec-
              tion system and substation design before allowing interconnection.
              Substation design was described in Chapter 11.

              Permits
              The critical issues analysis step identified the list of permits required
              and the agencies that issue them. In this task, activities related to
              obtaining the permits are performed. In most locations, all levels of
              the government get involved: Federal, state, and local. In an ideal
              situation, a one-stop comprehensive permit issued by single agency
              would eliminate the uncertainty around the permitting process. Some
              stateshaveasingleagencythatmanagesmostofthepermitting,except
              those that the federal agency has not delegated to the state agency.
              Following is a list of the most common permits:


                  1. Transportation permit. Turbine parts, construction equipment,
                    and cranes are large and heavy, requiring transportation
   344   345   346   347   348   349   350   351   352   353   354