Page 351 - Fluid Power Engineering
P. 351

Planning and Execution of W ind Projects     311


                    wetlands. Stormwater discharge permit will also be required
                    to discharge stormwater from construction activities. At the
                    federallevel,theUSArmyCorpofEngineersandtheEnviron-
                    mental Protection Agency regulate construction activity that
                    may harm the water resources; at the state level, the state envi-
                    ronmental quality agency administers the federal programs,
                    in addition to regulating state-specific resources.


              Logistics Planning
              Wind projects involve complex coordination and scheduling of tasks.
              This is especially true during the construction phase, which is com-
              pressed into a very tight timeframe. Poor logistics planning can
              be costly, because of the high cost of crane rentals, operators and
              setup, and, in general, high cost of capital. A wind project, like other
              projects, has complex relationships between different parts of the sup-
              ply chain. Wind projects work with just-in-time (JIT) manufacturing,
              JIT transportation with no inventories or storage, and JIT erection. The
              schedules must be coordinated between the civil contractor, turbine
              supplier, crane supplier, transportation contractors (with all three
              modes: water, rail, and road), electrical contractor, and others. How-
              ever,unlikeotherenergyprojects,weathercanplayabigrole.Rainand
              water logging can delay excavation and foundation work; rain, thun-
              derstorms, and high wind can delay erection of turbines. In some lo-
              cations, winds are so strong that erection cannot be done for 6 months.
              Therefore,iftheerectionwindowismissed,theprojectmaybedelayed
              for 6 months.
                 Logistics planning is further complicated because of shortage of
              most of the critical equipment and labor:

                    Turbine manufacturing has a long lead time

                    Trucks and railcars to transport oversized components are in

                    short supply and, therefore, difficult to schedule and resched-
                    ule. For a large utility-scale turbine, it takes 9 tractor trailers to
                    transport one turbine. Even for a single turbine, sequencing of
                    deliveries is critical to avoid logjam at a site that may not have
                    storage space. For instance, blades are scheduled to arrive af-
                    ter nacelle, which is scheduled to arrive after the towers.
                    Site supervision by turbine manufacturer is a specialized skill

                    that must be scheduled
                    Large 500- to 600-ton cranes and operators are in short supply

                    and the cranes are difficult to transport

                 A general contractor must, therefore, develop a detailed compre-
              hensive schedule, obtain regular updates from all task owners, update
   346   347   348   349   350   351   352   353   354   355   356