Page 355 - Fluid Power Engineering
P. 355

Planning and Execution of W ind Projects     315


              the constructed areas are graded and areas disturbed because of con-
              struction are restored to the original state by reseeding with native
              vegetation.
              Foundation Construction and Turbine Erection
              Foundation Construction
              The foundation design provides the specifications and instructions
              for foundation construction. From a project-planning perspective, the
              generic steps are:
                    Hundreds of cubic meters of soil is excavated or drilled and

                    blasted, depending on the type of soil.
                    An outer form is placed, followed by rebar, and then by a bolt

                    cage assembly along with conduits for cables and lightning
                    protection.
                    Concrete is then poured and cured. Curing time may be as

                    much as 1 month, depending on the size of the foundation.
                    The outer form is then removed and the area around the foun-

                    dation is backfilled and compacted.
                    In the middle of the foundation is an embed ring with bolts

                    sticking out. The tower is bolted to this embed ring.
                 A picture of partially complete foundation is in Fig. 14-4.




























              FIGURE 14-4 Spread foundation after concrete has been poured in the footing
              of the foundation. (Courtesy Vensys Energy AG.)
   350   351   352   353   354   355   356   357   358   359   360