Page 358 - Fluid Power Engineering
P. 358

318   Chapter Fourteen


              Collection System and Substation Construction
              This section pertains to construction and installation of the electrical
              infrastructure. A crew that specializes in electrical systems performs
              does these tasks.


                    Collection system. Most projects use underground power and

                    communications cables from the turbines to the substation.
                    Trenches are dug 4–6 ft deep and 1 ft wide. Power cables are
                    placed first and backfilled with soil that has acceptable ther-
                    mal resistivity. The communications cables are placed over
                    the power cables with several inches of backfill in the middle.
                    Specialized trucks are used for laying cables. If the backfill
                    soil does not have acceptable conduction properties to move
                    the heat, then the conductors can fail leading to expensive re-
                    pairs. Therefore, heat conductivity of soil must be tested and if
                    backfill soil is inappropriate, then alternate backfill material is
                    used. In addition, the cables must be inspected to ensure there
                    is no pinching of cables before the trenches are compacted.
                    Substation and maintenance building construction. Substation

                    normally contains pad-mounted transformer, metal-enclosed
                    switchgear, and other components like capacitors, if neces-
                    sary. In any electrical installation, the following are key to
                    safe operations: Proper grounding; testing of relay settings;
                    tight connections between conductors and equipment.
                    SCADA Systems. Installation and testing of SCADA system is

                    done before commissioning can start. This involves installa-
                    tion of all the telecommunications equipment, SCADA server,
                    SCADA software, and configuration. Testing of the SCADA
                    system involves testing if each device that is connected to the
                    SCADA system is able to:
                      Transmit status data when requested

                      Store operating data received from a device

                      Control of wind turbines based on stored logic

                      Communicate with external systems like grid operator, tur-

                      bine manufacturer, and others
                      Provide remote access

                      Generate reports

              Commissioning
              Commissioning of a wind farm is usually an elaborate handover pro-
              cess of the project from the contractor and turbine manufacturer to
              the project owner. The following entities are usually involved:
   353   354   355   356   357   358   359   360   361   362   363