Page 359 - Fluid Power Engineering
P. 359

Planning and Execution of W ind Projects     319


                    Turbine manufacturer, whose commissioning personnel per-

                    form the commissioning exercise
                    Contractor, whose civil and electrical personnel assist the tur-

                    bine manufacturer’s representatives with testing, monitoring,
                    and fixing
                    Project owner, who takes over and owns the project at the end

                    of commissioning
                    Wind farm operator, who operates and maintains the facility

                    for the project owner
                    Local utility, who will buy the energy produced by wind farm

                    Third-party independent expert, who works on behalf of the

                    project owner to oversee the commissioning process
                 To avoid problems, the types of tests and outcomes during com-
              missioning should be documented in the contract with the turbine
              manufacturer and the contractor. During contract negotiation, the tur-
              bine manufacturer’s or contractor’s preexisting checklist should be re-
              viewed, and this list, along with any modifications, should be added
              to the contract.
                 The objective of the commissioning phase is to ensure that the
              complete wind plant is safe to operate, is producing energy in a reli-
              able manner and of acceptable quality, and any outstanding defects
              have been identified. In addition, a plan of action has been agreed
              to by turbine manufacturer, contractor, and project owner to resolve
              outstanding issues. After the commissioning process, the ownership
              of the wind project turns over to the project owner. Typical criteria for
              passing the commissioning process are:
                  1. All the utility interconnection criteria are met. Prior to commis-
                    sioning, the local utility or the regional transmission operator
                    provideschecklistsandtheoperationsengineersfromtheutil-
                    ity/RTO inspect the plant. As an example, consider a two-step
                    procedure employed by Electric Reliability Council of Texas
                    (ERCOT) 3
                    a. Request to commission station. ERCOT provides a “request
                      to commission station” checklist. After conditions in the
                      checklist are met, it is submitted to the utility/RTO by the
                      operator. An approval and date of initial energize is issued
                      for the interconnection of the wind farm after the following
                      three conditions are met:
                         Sign off on the checklist by the utility/RTO

                         Resolution of all pending issues with utility’s operations

                         engineering
                         SCADA system is ready to monitor energy production
   354   355   356   357   358   359   360   361   362   363   364