Page 356 - Fluid Power Engineering
P. 356

316   Chapter Fourteen


              Erection
              Turbine manufacturer provides an erection plan along with crane re-
              quirements for erection. Normally, two cranes are used: A main crane
              with a rated capacity of 500– to 650 metric tons (for utility-scale tur-
              bines), and an auxiliary (or tail) crane with a rated capacity of 90
              metric tons. Typically, the main crane is a mobile crawler crane, while
              the auxiliary crane is a mobile hydraulic crane.
                 Turbine erection is a 2- or 3-day process per turbine. The first
              step in the process is to assemble the tower, which is in three or more
              sections.Figure14-5isaphotographshowingliftingofatowersection.
              Two cranes are used to lift the sections and stack them. After the tower
              sections have been stacked and bolted, the nacelle is lifted. Depending
              ontheturbinemanufacturer,therearetwooptionsforliftingofnacelle:
              (i) Single lift of nacelle with generator or (ii) two lifts: first, the nacelle
              is raised without a generator, then the generator is lifted and placed
              in the nacelle. The final assembly to be lifted is the rotor with blades.
              In order to prevent the blades from swinging and hitting the tower
              during the lift, various strategies are used including using two cranes
              working in tandem.


              FIGURE 14-5 Lifting
              of tower sections
              by the main crane
              (right). Auxiliary
              crane (left) assists
              with the lift.
              (Courtesy Vensys
              Energy AG.)
   351   352   353   354   355   356   357   358   359   360   361