Page 245 -
P. 245

7 - PROJECT COST MANAGEMENT






                           The SV and CV values can be converted to efficiency indicators to reflect the cost and schedule
                           performance of any project for comparison against all other projects or within a portfolio of projects. The
                           variances are useful for determining project status.
                        •   Schedule performance index. The schedule performance index (SPI) is a measure of schedule efficiency
                           expressed as the ratio of earned value to planned value. It measures how efficiently the project team is
                           using its time. It is sometimes used in conjunction with the cost performance index (CPI) to forecast the
                           final project completion estimates. An SPI value less than 1.0 indicates less work was completed than
                           was planned. An SPI greater than 1.0 indicates that more work was completed than was planned. Since
                           the SPI measures all project work, the performance on the critical path also needs to be analyzed to
                           determine whether the project will finish ahead of or behind its planned finish date. The SPI is equal to
                           the ratio of the EV to the PV. Equation: SPI = EV/PV                                           7

                        •   cost performance index. The cost performance index (CPI) is a measure of the cost efficiency of budgeted
                           resources, expressed as a ratio of earned value to actual cost. It is considered the most critical EVM
                           metric and measures the cost efficiency for the work completed. A CPI value of less than 1.0 indicates a
                           cost overrun for work completed. A CPI value greater than 1.0 indicates a cost underrun of performance
                           to date. The CPI is equal to the ratio of the EV to the AC. The indices are useful for determining project
                           status and providing a basis for estimating project cost and schedule outcome. Equation: CPI = EV/AC

                     The three parameters of planned value, earned value, and actual cost can be monitored and reported on both
                   a period-by-period basis (typically weekly or monthly) and on a cumulative basis. Figure 7-12 uses S-curves to
                   display EV data for a project that is performing over budget and behind the schedule.



                                                                                  Project Budget
                                                                                                   EAC
                                                          Management Reserve
                                                                                              BAC
                                                                    ETC

                                                                            Planned
                                   Cumulative Cost  Actual
                                                                            Value (PV)

                                           Cost (AC)
                                                          Earned
                                                          Value (PV)

                                                               Data Date
                                                          Time


                                        Figure 7-12. Earned Value, Planned Value, and Actual costs











                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   219
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   240   241   242   243   244   245   246   247   248   249   250