7 - PROJECT COST MANAGEMENT






                                              table 7-1. Earned Value calculations Summary table

                                                               Earned Value Analysis

                               Abbreviation  Name  Lexicon Definition  How Used     Equation    Interpretation of Result
                               PV     Planned   The authorized budget assigned to   The value of the work planned to be
                                      Value  scheduled work.   completed to a point in time, usually
                                                               the data date, or project completion.
                               EV     Earned Value  The measure of work performed   The planned value of all the work   EV = sum of the planned
                                             expressed in terms of the budget   completed (earned) to a point in   value of completed work
                                             authorized for that work.  time, usually the data date, without
                                                               reference to actual costs.
                               AC     Actual Cost  The realized cost incurred for the   The actual cost of all the work
                                             work performed on an activity during  completed to a point in time, usually
                                             a specific time period.  the data date.
                               BAC    Budget at   The sum of all budgets established   The value of total planned work, the
                                      Completion  for the work to be performed.  project cost baseline.
                               CV     Cost Variance  The amount of budget deficit or   The difference between the value of   CV = EV – AC  Positive = Under planned cost
                                             surplus at a given point in time,   work completed to a point in time,   Neutral = On planned cost
                                             expressed as the difference between  usually the data date, and the actual   Negative = Over planned cost
                                             the earned value and the actual cost. costs to the same point in time.
                               SV     Schedule   The amount by which the project is   The difference between the work   SV = EV – PV  Positive = Ahead of Schedule
                                      Variance  ahead or behind the planned   completed to a point in time, usually   Neutral = On schedule
                                             delivery date, at a given point in   the data date, and the work planned   Negative = Behind Schedule
                                             time, expressed as the difference   to be completed to the same point
                                             between the earned value and the   in time.
                                             planned value.
                               VAC    Variance at   A projection of the amount of budget  The estimated difference in cost at   VAC = BAC – EAC  Positive = Under planned cost
                                      Completion  deficit or surplus, expressed as the   the completion of the project.  Neutral = On planned cost
                                             difference between the budget at                 Negative = Over planned cost
                                             completion and the estimate at
                                             completion.
                               CPI    Cost   A measure of the cost efficiency of   A CPI of 1.0 means the project is   CPI = EV/AC   Greater than 1.0 = Under planned
                                      Performance   budgeted resources   exactly on budget, that the work     cost
                                      Index  expressed as the ratio of earned   actually done so far is exactly the   Exactly 1.0 = On planned cost
                                             value to actual cost.  same as the cost so far. Other values   Less than 1.0 = Over planned cost
                                                               show the percentage of how much
                                                               costs are over or under the budgeted
                                                               amount for work accomplished.
                               SPI    Schedule   A measure of schedule efficiency   An SPI of 1.0 means that the project  SPI = EV/PV  Greater than 1.0 = Ahead of
                                      Performance   expressed as the ratio of earned   is exactly on schedule,  that the work     schedule
                                      Index  value to planned value.  actually done so far is exactly the   Exactly 1.0 = On schedule
                                                               same as the work planned to be   Less than 1.0 = Behind schedule
                                                               done so far. Other values show the
                                                               percentage of how much costs are
                                                               over or under the budgeted amount
                                                               for work planned.
                               EAC    Estimate At   The expected total cost of com-  If the CPI is expected to be the same  EAC = BAC/CPI
                                      Completion  pleting all work expressed as the   for the remainder of the project, EAC
                                             sum of the actual cost to date and   can be calculated using:
                                             the estimate to complete.  If future work will be accomplished   EAC = AC + BAC – EV
                                                               at the planned rate, use:
                                                               If the initial plan is no longer valid,   EAC = AC + Bottom-up ETC
                                                               use:
                                                               If both the CPI and SPI influence the  EAC = AC + [(BAC – EV)/
                                                               remaining work, use:            (CPI x SPI)]
                               ETC    Estimate to   The expected cost to finish all the   Assuming work is proceeding on   ETC = EAC – AC
                                      Complete  remaining project work.  plan, the cost of completing the
                                                               remaining authorized work can be
                                                               calculated using:
                                                               Reestimate the remaining work from  ETC = Reestimate
                                                               the bottom up.
                               TCPI   To Complete   A measure of the cost performance   The efficiency that must be   TCPI = (BAC – EV)/(BAC – AC) Greater than 1.0 = Harder to
                                      Performance   that must be achieved with the   maintained in order to complete on     complete
                                      Index  remaining resources in order to meet  plan.      Exactly 1.0 = Same to complete
                                             a specified management goal,                     Less than 1.0 = Easier to complete
                                             expressed as the ratio of the cost to
                                             finish the outstanding work to the
                                             budget available.
                                                               The efficiency that must be   TCPI = (BAC – EV)/(EAC – AC) Greater than 1.0 = Harder to
                                                               maintained in order to complete the     complete
                                                               current EAC.                   Exactly 1.0 = Same to complete
                                                                                              Less than 1.0 = Easier to complete




             224      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®