Page 251 -
P. 251

7 - PROJECT COST MANAGEMENT






                   7.4.2.5 Project Management Software

                     Project management software is often used to monitor the three EVM dimensions (PV, EV, and AC), to display
                   graphical trends, and to forecast a range of possible final project results.


                   7.4.2.6 reserve Analysis


                     During cost control, reserve analysis is used to monitor the status of contingency and management reserves
                   for the project to determine if these reserves are still needed or if additional reserves need to be requested.
                   As work on the project progresses, these reserves may be used as planned to cover the cost of risk mitigation
                   events or other contingencies. Or, if the probable risk events do not occur, the unused contingency reserves   7
                   may be removed from the project budget to free up resources for other projects or operations. Additional risk
                   analysis during the project may reveal a need to request that additional reserves be added to the project budget.
                   Management and contingency reserves are addressed in more detail in Section 7.2.2.6.



                   7.4.3 control costs: outputs


                   7.4.3.1 Work Performance Information

                     The calculated CV, SV, CPI, SPI, TCPI, and VAC values for WBS components, in particular the work packages and
                   control accounts, are documented and communicated to stakeholders.


                   7.4.3.2 cost Forecasts


                     Either a calculated EAC value or a bottom-up EAC value is documented and communicated to stakeholders.


                   7.4.3.3 change requests

                     Analysis of project performance may result in a change request to the cost baseline or other components of the
                   project management plan. Change requests may include preventive or corrective actions, and are processed for
                   review and disposition through the Perform Integrated Change Control process (Section 4.5).


                   7.4.3.4 Project Management Plan updates

                     Elements of the project management plan that may be updated include, but are not limited to:














                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   225
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   246   247   248   249   250   251   252   253   254   255   256