Page 246 -
P. 246

7 - PROJECT COST MANAGEMENT






                      7.4.2.2 Forecasting

                         As the project progresses, the project team may develop a forecast for the estimate at completion (EAC) that
                      may differ from the budget at completion (BAC) based on the project performance. If it becomes obvious that the
                      BAC is no longer viable, the project manager should consider the forecasted EAC. Forecasting the EAC involves
                      making projections of conditions and events in the project’s future based on current performance information
                      and other knowledge available at the time of the forecast. Forecasts are generated, updated, and reissued based
                      on work performance data (Section 4.3.3.2) that is provided as the project is executed. The work performance
                      information covers the project’s past performance and any information that could impact the project in the future.

                         EACs are typically based on the actual costs incurred for work completed, plus an estimate to complete (ETC)
                      the remaining work. It is incumbent on the project team to predict what it may encounter to perform the ETC, based
                      on its experience to date. The EVM method works well in conjunction with manual forecasts of the required EAC
                      costs. The most common EAC forecasting approach is a manual, bottom-up summation by the project manager
                      and project team.

                         The project manager’s bottom-up EAC method builds upon the actual costs and experience incurred for
                      the  work  completed,  and  requires  a  new  estimate  to  complete  the  remaining  project  work. Equation:  EAC  =
                      AC + Bottom-up ETC.

                         The project manager’s manual EAC is quickly compared with a range of calculated EACs representing various
                      risk scenarios. When calculating EAC values, the cumulative CPI and SPI values are typically used. While EVM data
                      quickly provide many statistical EACs, only three of the more common methods are described as follows:

                            •   EAc forecast for Etc work performed at the budgeted rate. This EAC method accepts the actual
                              project performance to date (whether favorable or unfavorable) as represented by the actual costs, and
                              predicts that all future ETC work will be accomplished at the budgeted rate. When actual performance
                              is unfavorable, the assumption that future performance will improve should be accepted only when
                              supported by project risk analysis. Equation: EAC = AC + (BAC – EV)
                            •   EAc forecast for Etc work performed at the present cPI. This method assumes what the project has
                              experienced to date can be expected to continue in the future. The ETC work is assumed to be performed
                              at the same cumulative cost performance index (CPI) as that incurred by the project to date. Equation:
                              EAC = BAC / CPI





















             220      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   241   242   243   244   245   246   247   248   249   250   251