Page 247 -
P. 247

7 - PROJECT COST MANAGEMENT






                        •   EAc forecast for Etc work considering both SPI and cPI factors. In this forecast, the ETC work will
                           be performed at an efficiency rate that considers both the cost and schedule performance indices. This
                           method is most useful when the project schedule is a factor impacting the ETC effort. Variations of this
                           method weight the CPI and SPI at different values (e.g., 80/20, 50/50, or some other ratio) according to
                           the project manager’s judgment. Equation: EAC = AC + [(BAC – EV) / (CPI × SPI)]

                     Each of these approaches is applicable for any given project and will provide the project management team with
                   an “early warning” signal if the EAC forecasts are not within acceptable tolerances.


                   7.4.2.3 to-complete Performance Index (tcPI)

                     The to-complete performance index (TCPI) is a measure of the cost performance that is required to be achieved   7
                   with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to
                   finish the outstanding work to the remaining budget. TCPI is the calculated cost performance index that is achieved
                   on the remaining work to meet a specified management goal, such as the BAC or the EAC. If it becomes obvious
                   that the BAC is no longer viable, the project manager should consider the forecasted EAC. Once approved, the EAC
                   may replace the BAC in the TCPI calculation. The equation for the TCPI based on the BAC: (BAC – EV) / (BAC – AC).

                     The TCPI is conceptually displayed in Figure 7-13. The equation for the TCPI is shown in the lower left as the
                   work remaining (defined as the BAC minus the EV) divided by the funds remaining (which can be either the BAC
                   minus the AC, or the EAC minus the AC).


                     If the cumulative CPI falls below the baseline (as shown in Figure 7-13), all future work of the project will need
                   to be performed immediately in the range of the TCPI (BAC) (as reflected in the top line of Figure 7-13) to stay
                   within the authorized BAC. Whether this level of performance is achievable is a judgment call based on a number
                   of considerations, including risk, schedule, and technical performance. This level of performance is displayed as
                   the TCPI (EAC) line. The equation for the TCPI based on the EAC: (BAC – EV) / (EAC – AC). The EVM formulas are
                   provided in Table 7-1.






























                                                                                       ®
                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   221


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   242   243   244   245   246   247   248   249   250   251   252