Page 248 -
P. 248

7 - PROJECT COST MANAGEMENT








                                                             Status Date

                                                                                           TCPI
                                   >1                                                      (BAC)




                                   1.00                                                    Baseline Plan
                                                                                           TCPI
                                                                                           (EAC)
                                   <1
                                                                 Cumulative
                                                                 CPI

                                         Formula:
                                              Work Remaining (BAC-EV)
                                                                         = TCPI
                                          Funds Remaining (BAC-AC) or (EAC-AC)


                                               Figure 7-13. to-complete Performance Index (tcPI)


                      7.4.2.4 Performance reviews

                         Performance reviews compare cost performance over time, schedule activities or work packages overrunning
                      and underrunning the budget, and estimated funds needed to complete work in progress. If EVM is being used, the
                      following information is determined:

                            •   Variance analysis. Variance analysis, as used in EVM, is the explanation (cause, impact, and corrective
                              actions) for cost (CV = EV – AC), schedule (SV = EV – PV), and variance at completion (VAC = BAC – EAC)
                              variances. Cost and schedule variances are the most frequently analyzed measurements. For projects
                              not using earned value management, similar variance analyses can be performed by comparing planned
                              activity  cost  against  actual  activity  cost  to  identify  variances  between  the  cost  baseline  and  actual
                              project performance. Further analysis can be performed to determine the cause and degree of variance
                              relative to the schedule baseline and any corrective or preventative actions needed. Cost performance
                              measurements are used to assess the magnitude of variation to the original cost baseline. An important
                              aspect of project cost control includes determining the cause and degree of variance relative to the
                              cost baseline (Section 7.3.3.1) and deciding whether corrective or preventive action is required. The
                              percentage range of acceptable variances will tend to decrease as more work is accomplished.















             222      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   243   244   245   246   247   248   249   250   251   252   253