                    Table 3
                    Comparison of Calculated Values and Values Supplied by the Permit Application
                    for Condensation
                                                               a
                                                  Calculated value (example case)  Reported value
                    Continuous monitoring of exit       Yes                             —
                      stream temperature
                    Condensation temperature, T         20ºF                            —
                                           con
                    Coolant type                        Brine solution                  —
                    Coolant flow rate, Q                14,700 lb/h                     —
                                     coolant
                    Condenser surface area, A           370 ft 2                        —
                                         con
                    Refrigeration capacity, Ref         20 tons                         —
                    Recovered product, Q                373 lb/h                        —
                                      rec
                       a Based on emission stream 6.


                    Table 4
                    Capital Cost Factors for Condensers
                                    Cost item                              Factor
                         Direct Costs
                           Purchased Equipment Costs
                              Condenser and auxiliary equipment          As estimated, EC
                              Instrumentation a                          0.10 EC
                              Sales tax                                  0.03 EC
                              Freight                                    0.05 EC
                                Purchased Equipment Cost (PEC)           1.08 EC
                           Direct Installation Costs
                              Foundation and supports                    0.08 PEC
                              Erection and handling                      0.14 PEC
                              Electrical                                 0.08 PEC
                              Piping                                     0.02 PEC
                              Insulation                                 0.10 PEC
                              Painting                                   0.01 PEC
                                Direct Installation Cost                 0.43 PEC
                              Site preparation                           As required, SP
                              Buildings                                  As required, Bldg.
                                Total Direct Costs (DC)                  1.43 PEC + SP +Bldg.
                         Indirect Installation Costs
                           Engineering                                   0.10 PEC
                           Construction                                  0.05 PEC
                           Contractor fee                                0.10 PEC
                           Start-up                                      0.02 PEC
                           Performance test                              0.01 PEC
                           Contingencies                                 0.03 PEC
                                Total Indirect Cost (IC)                 1.31 PEC
                         Total Capital Costs b                           1.74 PEC + SP + Bldg.
                       a Typically included with the condenser cost.
                       b Does not include cost of refrigeration system.
                       Source: Data from refs. 4 and 9.