Page 281 - APPLIED PROCESS DESIGN FOR CHEMICAL AND PETROCHEMICAL PLANTS, Volume 1, 3rd Edition
P. 281

Mechanical Separations                                    253




                                                                                   t
                                                            -+





                              =I---

                                         HORIZONTAL  SEPARATORS      HORIZONTAL SEPARATORS





                             ?













                                         iM-LINE  GAS  SCRUBBERS     OIL-GAS  SEPARATORS     OVER-SIZE  VESSEL
                       Figure 41-24.  Typical mesh installations in process equipment. Courtesy of Metal Textile Gorp., Bulletin ME-7.


            selected, the heads normally available for such vessels run   Use stainless 304 mesh due to low temperature opera-
            in 6-inch increments (either Q.D.  or I.D.).         tion. Carbon steel is too brittle in wire form at this tem-
              Net inside diameter at support ring:               perature.
                                                                    The check or specification form of Figure 426 is nec-
                    . - 4” - 3,/4” = 25 1/4“                     essary and helpful  when  inquirying  wire  mesh  entrain-
                                                                 ment units,  either  as the  mesh  alone, or as  a complete
              Note that vessel wall assumed %inch thick.         turnkey unit including vessel.
              Net area = 3.46 sq ft
                                                                    For services where solids are present or evaporation of
                                                                 droplets on the mesh might leave a solid crust, it is usual
                                                                 practice to install sprays above or below the mesh to cover
             Actual velocity at ring:  2.83 (2.74) = 2.24 ft / sec
                                 3.46                            the unit with water (or suitable solvent) on scheduled (or
                                                                 necessary)  operating  times,  as  the  plugging builds  up.
                      esign melocity: 2.24(100)/3.66  = 61.3%. This   This is checked by a manometer or other differential pres-
           is acceptable operating point.                        sure meter placed with taps on the top and bottom side of
              Note that if 28-inch O.D. X %-inch ~7all pipe is available   the mesh installation.
           this could be used with weld cap ends, or dished heads.   A few case examples for guidance include:
           The percent design velocity would be = 71.8%.
              This is also an acceptable design.
              Pressure drop is in the order of  0.1 inch to 0.5 inches   0  2-3%  caustic solution with  10% sodium  carbonate.
                                                                     This  condition  might  plug  the  wire  mesh.  Sprays
           water.                                                    would be recommended.
           Notes: Since this vessel will operate as a flash drum with
           a liquid  level at approximately >i of  its height up from   e Raw river water. This presents no plugging problem
           bottom, place the inlet at about center of vessel. See Fig-   Light hydrocarbon  mist. This presents  no plugging
           ure 4-25.                                                 problem
   276   277   278   279   280   281   282   283   284   285   286