Page 359 - Beyond Decommissioning
P. 359

Case studies of nuclear redevelopment                             335

           sampling and laboratory support personnel were not immediately advised of this
           change in RCRA status for waste generated at the site. Failure to communicate the
           change in RCRA status in a timely manner resulted in the improper handling of poten-
           tial U- and F-listed waste.
              Analysis: A management failure to communicate, in a timely manner, a substantial
           change in regulatory status to all impacted personnel has been identified as the pri-
           mary cause of this event.
              Lessons learned: Changes in the regulatory status of environmentally regulated
           areas (RCRA, CERCLA, etc.) in and around US Department of Energy (DOE) facil-
           ities should be communicated to all personnel who direct or perform work in the sub-
           ject areas. Failure to keep personnel updated on current regulatory status could result
           in violations of procedural and/or regulatory requirements.



           7.14.8 Redevelopment and reuse complicated by drains legacy,
                   United Kingdom (International Atomic Energy Agency,
                   2011)
           Problem encountered: A large nuclear research site with hundreds of buildings used a
           network of drains, developed over decades, to link the buildings to a central liquid
           effluent treatment plant. The drains included:
           –  pipes dissipating wastewater into the soil (soakaways);
           –  industrial effluent systems, which were designated as radiologically inactive;
           –  old active drains with no secondary barriers;
           –  modern active drains with secondary barriers; and
           –  rainwater drains.
           Problems included:
           –  overlapping of different types of drains and delay tanks, which had been installed with no
              decommissioning of old systems;
           –  drains collapsed or leaking;
           –  inactive drains inadvertently used for active effluents;
           –  drains that were not recorded on site drawings;
           –  some drains had been decommissioned but no records were made of their location, contam-
              ination found, etc.;
           –  some drains had been grouted in situ with insufficient records; and
           –  rainwater was penetrating into drains creating unneeded effluent.

           Solution found: A program of drains decommissioning was established to allow site
           redevelopment. The remaining buildings requiring drainage were segregated and had
           dedicated systems. The remaining network of drains was decommissioned, which
           included the following activities:
           –  identification and mapping;
           –  use of a geographical information system to record and map progress;
           –  flushing of drains;
           –  contamination monitoring using a pipe crawling robot;
   354   355   356   357   358   359   360   361   362   363   364