Page 16 - Boiler plant and distribution system optimization manual
P. 16

Chapter 1



                                           Boiler Plant Orientation

                                                          [Fast Track]








                MODERN BOILERS                                      dom detected.
                                                                         When water is heated to form steam we are
                     Modern boiler designs go back well over 100    restricted to certain temperatures for the steam.
                years. It has been a century of changes in design,   This pressure-temperature relationship is called
                construction and operation of boiler plants. Pres-  the saturation temperature. Simply stated, all of
                sure vessel design has advanced from riveted to     the  heat  transferred  to  the  water  just  generates
                welded  construction.  Natural  draft  firing  using   more steam. If we want to raise the temperature
                tall brick stacks has given way to forced draft and   of the steam above the saturation temperature we
                balanced draft operations. Controls have taken      take the water out of the process and apply heat
                over most of the tedious watchstander functions     to steam only. The steam now becomes superheat-
                and now computerized systems can almost think       ed as shown on the right-hand side of Figure 1.1.
                for plant personnel.                                     When steam is generated in a pressure vessel,
                                                                    the same process occurs but conditions change.
                                                                    Figure 1.2 illustrates when steam is generated at
                GENERATING STEAM                                    3,000 psi (200 Bar). The saturation [boiling] tem-
                                                                    perature is now 695°F. It takes a lot more Btus to
                     Boilers must deliver dry clean steam at a      heat  the  water  to  the  boiling point, but it takes
                specified  pressure  and  temperature.  Figure  1.1   fewer Btus to form a pound of steam. At atmo-
                shows the basic steam generation cycle. The Brit-   spheric pressure it takes 970 Btus and at 3,000 psi
                ish thermal unit (Btu) is a term used to identify   it takes only 213 Btus. The difference is the 802
                the heat value of fuel and steam. The scale begins   Btus needed to bring the water up to the boiling
                at  the  freezing  point  for  water  or  32°F.  Adding   point at 695°F for this high pressure.
                one Btu to a pound of water will raise its temperature      Table 1.1 illustrates the relationship of pres-
                1°F. It takes 180 Btus to heat water from the freez-  sure and energy values. It shows the information
                ing point to the boiling point, but we don’t have   available from standard steam tables, a source of
                steam  yet. At  atmospheric pressure it takes an    essential information  about  the  properties  of
                additional 970 Btus to form one pound of steam.     steam. Engineers use steam table values for the
                This steam is the energy that goes to work for us.   design and operation of steam plants.
                When the pound of steam, with its 970 Btus, gives
                up its heat in the steam distribution system and
                condenses  back  into  water,  its  volume  shrinks   TYPES OF BOILERS
                tremendously to 1/700  its steam volume. High
                pressure  replacement  steam  rushes  in  to  fill the   Package boilers are used for most commer-
                void caused by the shrinkage in volume caused       cial and smaller industrial operations. They are
                by the steam to water phase change. Because this    built at a factory and then shipped to the plant
                process is continuous and the replacement steam     via truck, barge and railroad. They are usually
                moves in very quickly, pressure changes are sel-    complete units which need only be connected up