Page 524 - Corrosion Engineering Principles and Practice
P. 524
490 C h a p t e r 1 2 C o r r o s i o n a s a R i s k 491
Safety and Environmental Perspective Incident rate • Safety performance index • PHA/reviews completed (total) • PSM compliance audits (total) • Significant environmental aspects • defined/quantified (total) Outstanding items from monthly safety • inspection report (total) A incidents (tot
Work Management Perspective Planning compliance • Work order complete (within 20 • percent of planned costs) Proactive work orders (%) • Scheduling compliance • Assessments of work order • complete (total) Quantified availability targets (total) • Emergency work orders (%) • Reactive
Reliability Perspective Plant availability • Proactive work orders (%) • Emergency work orders on high • critical systems (%) Significant deterioration • mechanisms improvements Inspection compliance • Protective device schedule • compliance Quantified reliability target (total)
Operations Perspective Strategic KPI Plant availability • Number LPO events • Time operating outside • deterioration limits (%) Plant uptime (%) • Production target • compliance Operational KPI Process availability • variance Utility variance • Product transfer indicator •