Page 311 - Defrosting for Air Source Heat Pump
P. 311

306                                         Defrosting for Air Source Heat Pump


          Table 10.1 Parameters of the ASHP unit used in this study
          Item        Parameters                       Value             Unit

          1           Rated cooling capacity           5.2               kW
          2           Rated heating capacity           6.5               kW
          3           Rated cooling power consumption  1600              kW
          4           Rated heating power consumption  1840              kW
          5           Rated cooling COP                3.25              –
          6           Rated heating COP                3.53              –
          7           Brand                            Daikin            –
          8           Model name of indoor unit        FTXD50FVM         –
          9           Total price in Harbin, China     $1200             USD




         accumulation on the surface of a circuit could be changed, and thus the FEC can be
         improved. In addition, under each circuit, water-collecting trays were placed by which
         the melted frost could be collected. After the frost that accumulated on the surface of
         each circuit melted, the water flowed into a measuring cylinder, which contacted the
         corresponding tray. And thus, these frosts could be weighed and calculated. With this
         method, as reported in previous energy studies [2–4], the frosting and defrosting per-
         formances of an ASHP unit could be effectively improved after the valves were
         installed. The experimental ASHP unit was installed in an existing environmental
         chamber having a simulated heated indoor space and a simulated outdoor frosting
         space. The sizes of both spaces were each measured at 3.8 m (L)   3.8 m (W)
         2.8 m (H). The three-circuit outdoor coil was installed in the outdoor frosting space,
         where the frosting/defrosting cycle operations were carried out. Detailed experimental
         procedures and conditions were previously reported.
            In a frosting/defrosting cycle, the frosting operation came out first. After the valves
         were installed, the frosting performance would be effectively optimized. Therefore,
         frosting experiments should be first undertaken before the defrosting experiments
         in this study. As listed in Table 10.2, two frosting experimental cases were designed.
         Valves and trays were both installed, and thus different FECs, FEC 1 and FEC 2 , could
         be reached. The frosting duration was fixed at 60 min. With this experimental study,
         the frosting operating performances of an ASHP unit at different FECs could be
         obtained. Valves in Case F1 were fully open, and the FEC 1 was less than 100%
         due to the refrigerant and air being unevenly distributed. Differently, the valves in
         Case F2 were evenly adjusted, and thus the FEC 2 was nearly 100%.



          Table 10.2 Two frosting experimental cases
          Case No.                     Case F1             Case F2
          Valves (Status)              With (Fully open)   With (Evenly adjusted)
          FEC                          FEC 1 (<90%)        FEC 2 (90% 100%)
          Frosting duration            60 min              60 min
          Condition shown in Fig. 10.2  (A)                (B)
   306   307   308   309   310   311   312   313   314   315   316