380   Chapter Ten

        technologies such as the World Wide Web and Intranets may be used as the
        medium for access to the process manual.
        Many processes will require the hiring of new employees with certain
        specific skills and the purchase of specialized tools or equipment. Following
        the specifications of the process design, such employees can be hired and
        the equipment purchased. Procuring long-lead-time equipment or hiring
        employees with hard-to-find skills should start early so that everything can
        be in place for the process to commence operation. Installation of equipment
        should follow recommended procedures, and new employees should be
        trained quickly so that they can be at their most effective as soon as possible.

        10.6.6 Process Maintenance

        Process maintenance involves ongoing monitoring of the process, as well as
        periodic improvements to ensure that process performance remains high
        despite changing internal and external conditions. After the process has
        been implemented, it should not just be abandoned to its fate. Rather, the
        process should be treated like one would treat any other valuable asset of the
        organization; track its performance over time and schedule periodic
        reexamination to determine if it needs any major or minor overhauls. This
        maintenance will ensure that if conditions were to change or tools and
        equipment were to wear out, an opportunity would be available to update
        the process and cope with the new requirements. For tracking and process
        monitoring, it is recommended that, at the minimum, the most important of
        the performance metrics considered in the process design should be tracked.
        In addition, other data providing early warnings regarding the state of the
        process should be collected.

        For example, for critical equipment, failure times and downtime durations
        should be logged. Data collection systems or data tracking forms need to be
        designed for acquiring the data of interest. All statistical process control
        activities for the process are an integral part of the process maintenance.
        Maintenance schedules for important equipment should be based on the
        frequency recommended by the manufacturers of the equipment.


        10.7 A Process Management Case Study

        10.7.1 Background
        This case study is from Mejabi (2003). USAA is an insurance company that
        started losing market share due to price competition from competitors and