Page 144 - Design of Simple and Robust Process Plants
P. 144

4.2 The Methodology of Process Synthesis  129
                      cess heat can be generated at a steam level between the utility levels, for usage
                      at another plant section a plant intermediate steam level might be appropriate.
                   5.  Develop a plant energy system which is largely independent from external
                      steam supply, without violating the benefits of site integration. This to reduce
                      its vulnerability, the transfer of large amounts of steam across the site and its
                      related dynamic effects.
                   6.  For network integration, the following implementation rules need to be
                      applied:
                      ±  Apply process integration in the following order of priority: unit, section,
                         process, site (complex).
                      ±  Apply heat exchange between flows of similar heat capacity (mass flow ”
                         specific heat, M ” C p ) are preferred, rule of Gommers.
                      The inlet and outlet streams of reactor systems are often counter currently
                      crossed as well as the inlet and outlet of a furnace (air pre-heater with flue
                      gas). Another example is the exchange between solvent streams of inlet and
                      outlet of absorber/desorber. The above examples comply with the integration
                      per unit/section, and will also give close to parallel temperature profiles
                      which lead to limited number of exchangers.
                      ±  Apply process simplification in relation to process integration, avoid pro-
                         cess stream splitting unless operability and controllability problems are
                         adequately solved while saving are considerable.
                   7.  Develop a strategy for drivers in the process (electrical versus steam versus
                      gas turbine, which fit in the site infrastructure). The desire to avoid a com-
                      mon cause failure is a point for consideration

                The above approach is applied during process integration 1, and upgraded at step 2.
                 During process integration 1, the preliminary energy structure is developed and the
                 energy values for the different steam levels must be determined as these need to be
                 used for the level 2 reactor and separation synthesis. In step 2, the challenge is to
                 adapt the process conditions to minimize the energy targets before energy integra-
                 tion is applied.

                 4.2.3.5  Simplification with integration
                 During the development of an energy structure it is important to avoid many cross-
                 connections and ultimately to keep a well-ordered process. This is one of the reasons
                 why operability and controllability were introduced as constraints for integration.
                The following basic rules are to be applied:
                   .  The application of an order of priority for process integration from unit, section,
                      process and complex is one of the starting points for process simplification.
                   .  The application of heat exchange between flows of similar heat capacity
                      (mass flow ” specific heat).
                The design philosophy of clever process integration finds its starting point here. In
                 this section, some reference is made to simple design solution that is specific for
                 energy integration.
   139   140   141   142   143   144   145   146   147   148   149