420  Chapter 10 The Efficient Design and Continuous Improvement of High-quality Process Plants
                step, the main functions involved, and its responsibility in the step. It also contains
                references such as company procedures. An example of a short step-wise description
                for the development of a plot plan for a new facility is shown in the Appendix 10.1.
                  Decision and review steps are part of the work process. The reviews are technical
                as well as organizational A good work process is a feed-forward controlled concept
                with feed-back loops built in (In't Veld, 1985) (Figure 10.3). This says that the work
                process needs to capture up-front activities or procedures to avoid rework from the
                reviews. The overall concept is: ªdo things right the first timeº.


                                Project approach

                  Feed - forward controller        Feed - back controller
                                                         setpoint






                                     Process


                Fig. 10.3. An efficient controlled process has a feed-forward
                controller with a feed-back adjustment.



                10.3.1.1  The development of a work process
                The development of a work process (WP) needs to follow a set of rules to assure the
                quality of the work. The development team needs to have the following key ele-
                ments:
                  .   Scope of work
                  .   Development methodology
                  .   Independent moderator
                  .   Highly qualified members of all functions involved. All functions involved
                      should be represented by highly qualified people; (it might be worthwhile to
                      introduce external company representatives during the development if they
                      play a role in the work process).
                Some key words for people involved in the development are: open minded, with a
                mandate for decision; and respect for each other.
                  A fully developed WP should have as end result:
                  .   Flow diagram
                  .   Step descriptions
                  .   Owner assigned
                  .   Maintenance system