188 Section Four—MECHANICAL INSTRUMENTATION
CONNECTING PNEUMATIC PANEL BOARD INSTRUMENTS
MAN HOURS EACH
Man Hours
Description Each
Recording Controller— large case 12" circular chart, with automatic reset,
one pen, one controller 4,4
two pens, one controlling, one recording only 6.6
two pens, two controllers 8.8
three pens, two controlling, one recording only 11,0
Receiving Recorder— large case 12" circular chart, one pen 2.7
two pens 3.3
three pens 5.0
Receiving Indicator — concentric dial 3-/£" circular case
ribbon type, horizontal or vertical 4" scale 1.7
ribbon type, for two variables 3.3
Manual Loading Station — 6" x 5-14" with circular dial and horizontal
output indicator:
one pointer diaphragm element 2.2
two pointers diaphragm element 3.3
two pointers diaphragm element with set point
regulator 4.4
two pointers diaphragm element with set point
regulator and auto ./man. unit 5.0
l
Recorder — 7-W x 7-A", 4" strip chart:, one pen 2.2 ""
two pens 3.3
three pens 5.0
Recording Control Station — 7-W x 7-/4", 4" strip chart and vertical
output gauge:
one pen 4.4
one pen, one pointer 4.4
two peris 8.8
two pens, one pointer 8.8
three pens 13.2
Controller — Shelf Mounting: proportional control 3.3
proportional control plus derivative control 4.4
proportional control plus reset control 4.4
proportional control plus reset plus derivative control 4.4
Above man hours include making tubing terminal connections, calibrating, checking, adjusting, testing, and commis-
sioning pneumatic instruments.
Mail hours for installation of air supply piping and air signal lines from control panel to remote instruments are not
included. See other accounts for these man hours.
No manufacturer's representatives are included in the above man hours.