Page 209 - Estimators Piping Man Hour Manual
P. 209
192 Section Five—UNDERGROUND PIPING
HAND EXCAVATION
NET LABORER MAN HOURS PER CUBIC YARD
First Second Third
Soil Excavation Lift Lift Lift
General Dry 1.07 1.42 1.89
Light General Wet 1.60 2.13 2.83
Special Dry 1.34 1.78 2.37
General Dry 1.60 2.13 2.83
Medium General Wet 2.14 2.85 3.79
Special Dry 1.07 2.49 3.31
General Dry 2.67 3.55 4.72
Hard or Heavy General Wet 3.21 4.27 5.68
Special Dry 2.94 3.91 5.20
General Dry 3.74 4.97 6.61
Hard Pan General Wet 4.28 5.69 7.57
Special Dry 4.01 5.33 7.09
Man hours include picking and loosening where necessary and placing on bank out of way of ex-
cavation or loading into trucks or wagons for hauling away. Man hours do not include hauling
or unloading.