Section  Five—UNDERGROUND PIPING        193

                           ROCK      EXCAVATION







                                                Labor  Hours per  Cubic Yard
              Operation                   Soft          Medium           Hard

     Hand Drill, Plug and Feathers       15.0            21.0            30,0
     Hand Drill, Blasting                13.0            16.0            22.0
     Machine Drill, Plug and Feathers     8.0            11.0            14.0

     Machine Drill, Blasting              4.0             6.0             7.0

     Man hours  are  for  above described operations only.
     For  hauling see  respective man hour  page.
     Equipment and materials must be added in all cases.












     Operation                  Laborers         Carpenters        Truck Drivers

     Placing                       3.0              3.0               0.4
     Removing                      2.5                                 0,4
                                                    —

     Man hours  include hauling, erecting and stripping.