Page 212 - Estimators Piping Man Hour Manual
P. 212
Section Five—UNDERGROUND PIPING 195
Hand Shovel Bulldoze Tamped
Soil Placed Placed 6" Layers
Light 0.60 0.04 ...
Medium 0.80 0.07 1.00
Heavy 1.00 0.10 i.io
Man hours for hand shoveling and tamping is that of common labor. Man hours for bulldozer
placing is that of operating engineer.
All man hours are based on backfill materials being located within shoveling distance of exca-
vated area.
UNDERGROUND ISO LBS. B. & S. CAST IRON PIPE
LABOR m MAN HOURS
MAN HOURS PER FOOT PER MAKE-ON
150 Lb. B & S Fittings
Size Pipe Set Lead & Mech. Cement Sulphur
Inches & Align Joint Joint Joint
4 0.09 0.50 0.35 0,25
6 0.11 0.57 0.37 0.29
8 0.14 0.70 0.50 0,35
10 0.17 0.85 0.60 0.43
12 0.24 1.23 0.95 0.62
14 0.35 1.78 1.25 0.89
16 0.45 2.28 1.60 1.14
18 0.53 2.68 1.89 1.34
20 0.63 3.19 2.24 1.59
24 0.79 4.00 2.81 2.00
Pipe man hours includes handle, haul, set and align in trench.
Fitting man hours includes one make-on.
Man hours must be added for excavation. See respective pages for this charge.