196     Section Five—UNDERGROUND PIPING

               UNDERGROUND             VITRIFIED      CLAY AND
                               CONCRETE        PIPE


                                 LABOR IN  MAN HOURS


                            CONCRETE PIPE
                             (Not Reinforced)        VITRIFIED CLAY  PIPE
                        Set  & Align   Cement      Set  & Align
             Size          Pipe        Poured         Pipe        Poured
            Inches       Per  Foot    Joint Each    Per  Foot    Joint Each

              4           0.07          0.20         0.07          0.25
              8           0.08          0.25         0.07          0.29
              8           0.10          0.32         0.07          0.35
              10          0.11          0.39         0.08          0.43
              12          0.15          0.50         0.10          0.82
              15          0.19          0.75         0.11          0.89

              18          0.28          0.95         0.14          1.14
              21          0.29          1.15         0.19          1.38
              24          0.32          1.25         0.25          1.63
              30          0.40          1.56         0,31          2.04
              36          0.48          1.88         0.37          2.44
              42          0.56          2.19         0.44          2.85
              48          0.64          2.50         0.50          3.26
              60          0.80          3.13         0.62          4.0?


      Man hours includes handle,  haul, set  in  trench  and align.  Man hours for joint  or  connection of
      fittings  is  for  one make-up only.
      No  labor  for  excavation or  backfill is  included.  Add from  respective pages for these charges.
      For  reinforced  concrete  pipe  add 5% to man hours listed for  concrete  pipe.