Page 60 - Forensic Structural Engineering Handbook
P. 60
TABLE 1.3 Council of American Structural Engineers Drawing Review Checklist (Continued)
Project: Project Manager: Reviewer:
Project No.: Engineer: Date:
Item Yes No N/A Comment
IV. Mechanical/Electrical and
Plumbing/Structural
A. Checked storm drain system against
structural floor and foundation
plan?
B. Checked HVAC floor plans
against structural for floor and
wall openings?
C. Checked that all structural supports
required for mechanical equipment
are indicated on structural
drawings?
D. Verified all roof penetrations
(ducts, etc.) have framing to support
adjacent structure?
E. Checked underground utility line
locations for interference with
foundations?
F. Verified that toilet layout and pene-
trations do not conflict with beams
and joist (both steel and concrete)?
G. Does imbedded conduit conform to
ACI 318?
H. Checked light fixture interference
with structural framing?
V. Structural Drawings
A. Are notes complete, showing design
criteria, building code references,
floor loads, material strengths, and
allowable foundation pressure?
B. Are requirements for special inspec-
tions included?
C. Do drawings conform to design cal-
culations and sketches?
D. Are notes consistent with sections
and details?
E. Do notes provide necessary design
information for prefabricated items?
1.41