Page 22 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 22

List of Lessons Learned










              Chapter 1 Project Lessons Learned                     2.8: Critical centrifugal pumps and ‘bad actor’ pumps
                                                                        require operator surveillance.
               1.1: Failure to incorporate ‘Lessons Learned’ during the pre-  2.9: Centrifugal pump flow is determined by the head
                   FEED phase of the project.                           required by the process.
               1.2: Failure to establish project team support early in the  2.10: Failure to install discharge orifices in high speed pumps
                   project.                                             reduces MTBF.
               1.3: Not screening vendors for experience for the project.  2.11: Pump NPSH margins are traditionally set for only the
               1.4: Failure to consider the proper selection and design of  rated operating point.
                   each item in the equipment train.               2.12: Selecting a pump for NPSH required without
               1.5: Excessive specs and incomplete data sheets reduces  considering suction specific speed.
                                                                   2.13: Pump bearings with a DN number above 350,000 are
                   safety, reliability and plant revenue.
               1.6: Absence or lack of ITB vendor instructions results in  prone to low bearing MTBF.
                   endless meetings and emails.                    2.14: Optimum MTBFs for high DN pumps is not possible
               1.7: 80% of machinery failures are due to process changes  without continuous lubrication.
                   not considered in the design phase.             2.15: Many pump failures have been caused by poorly
               1.8: Failure to have pre-bid meetings will reduce critical  designed temporary suction strainers.
                   machinery safety and reliability.               2.16: EP&Cs and end users do not have guidelines for the use
               1.9: Using the EP&C typical bid tabulation format extends  of min. flow bypass valves.
                   the bid cycle time.                             2.17: Low centrifugal pump flow results in pump damage and
              1.10: Poorly planned pre-award meetings will affect project  exposure to safety issues.
                   schedule and result in cost adders.             2.18: Internal type bypass valves can fail to open at the
                                                                        minimum flow set point.
              1.11: Poorly planned VCMs will result in cost adders and
                   delivery schedule extensions.                   2.19: Centrifugal pumps operating in parallel are prone to
                                                                        damage from liquid vaporization.
              1.12: Failure to conduct timely design audits affects
                   machinery safety and/or reliability.            2.20: Excessive pump flange and foundation forces will lead
              1.13: Inefficient vendor and EP&C document reviews will    to low bearing MTBF.
                   cause delivery delays.                          2.21: Many pumps have impellers that are too large for field
              1.14: Failure to conduct an effective FAT will expose the end  operation parameters.
                   user to future reliability issues.              2.22: Lack of a plant spare changeover philosophy reduces
                                                                        pump MTBFs.
                                                                   2.23: Impeller diameter increases have resulted in driver and/
                                                                        or coupling overloads.
                                                                   2.24: Controlling centrifugal pumps with control valves is not
              Chapter 2 Pump Lessons Learned                            energy efficient.
                                                                   2.25: Operators need to understand the use of centrifugal
               2.1: Not using lessons learned to select the pump will lead to  pump test curves.
                   lower pump reliability.
               2.2: Letting the EP&C select pumps can lead to lower pump
                   reliability.
               2.3: Changes in operating conditions will cause lower pump
                   reliability.                                    Chapter 3 Compressor Lessons
               2.4: Leaving pump case design to the EP& C can lead to field  Learned
                   safety and reliability issues.
               2.5: Double suction pumps have the greatest amount of field  3.1: Improper compressor selection will reduce safety and
                   reliability problems.                                reliability.
               2.6: Operating an inducer pump outside its BEP by more  3.2: Inaccurate process conditions cause project scope
                   than +/- 10% lowers reliability.                     changes and increase delivery time.
               2.7: Failure to establish EROE limits will lead to low MTBF  3.3: Failure to use the proper case design and number of
                   of centrifugal pumps.                                impellers reduces reliability.

                                                                                                                xxi
   17   18   19   20   21   22   23   24   25   26   27