Page 309 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 309

Be st Practice 5 .10          Steam Turbine Best Practices
       B.P. 5.10. Supporting Material                         The success of the shop test depends on a good test plan that
                                                            is reviewed by the end user and contractor and modified as
                                                            requested well in advance of the test. Figure 5.10.3 presents
       Testing phase                                        these facts.

       The testing phase is the last phase in terms of vendor and sub-
       supplier design and manufacturing involvement in the project e
       and so it is the last chance to ensure the optimum availability of
                                                                The agenda is issued for review two months prior to test
       the finished product.                                     It incorporates agreed VCM scope
          Remember that all of the equipment addressed in this section  Compressor performance test conditions are per ASME PTC–
       is most likely custom designed, and no matter how much ac-  10 requirements
       crued design and manufacturing experience is present, the  A sample of test calculations and report format is included
       possibility of some abnormality, hopefully minor, is high.  Vendor concurs with all end user and contractor comments
                                                                prior to test
       Therefore, it is imperative that this phase be carefully observed
       and witnessed by the end user team. Figure 5.10.1 lists impor-
       tant facts surrounding this phase of the project.    Fig 5.10.3   Shop test agenda review – key facts


                                                              I actually began my career in rotating equipment on the test
                                                            floor. And I can still remember how we would see the witnesses
        The shop test is an opportunity to:                 come in with an intent to completely participate in the entire
           Con fi rm vendor proper design and manufacture    test, only to leave for a long ‘test lunch’ an hour or so later. Why
           Match field conditions                            did this occur? Usually because the concerned end user and
           Witness assembly and disassembly using job special tools  contractor witnesses did not have the opportunity to review the
           Have plant personnel observe test, assembly, etc. and take
                                                            test set-up and the procedure prior to the test. As a result, I have
           pictures for purposes of emergency fi eld maintenance
           excellence                                       always been a proponent of a pre-test meeting.
                                                              Is it always required? I think it is but the detail and timing of
           Review the instruction book
           Have the assigned vendor service engineer observe the   the meeting depends on certain factors. These factors are noted
           equipment he will install                        in Figure 5.10.4.
           Review all vendor fi eld procedures

       Fig 5.10.1   The shop test
                                                                If the equipment is prototype
                                                                If the equipment is complex
                                                                If a full load test is required
          A shop test checklist is included at the end of this best  If the test facility is new
       practice that will be valuable in planning and executing the shop
       test phase. Yes e there certainly are many opportunities to
       ensure equipment reliability during shop test, but there are also  Fig 5.10.4   When is a pre-test meeting required?
       a lot of potential lost opportunities if they are not justified to the
       project team early, during the pre-FEED phase, of the project.  If it is decided to conduct a pre-test meeting, the key facts are
       The potential lost shop test phase opportunities are noted in  noted in Figure 5.10.5.
       Figure 5.10.2.




                                                                Conduct the meeting prior to the test day
                                                                Send the agenda to the vendor well in advance
        The following opportunities will be lost if they are not justified at  A typical agenda outline:
        project inception:                                        Confirm test agenda requirements
           Possible full load test                                Confirm all test parameter acceptance limits
           Unproven component tests                               Confirm instrument calibration
           Attendance at test by plant personnel                  Review test set up or concept drawing
           Use of special tools                                   Review data reduction methods
           Vendor permission for pictures                         Confirm all test program agreements
           Agreement that assigned vendor fi eld service specialists will be
           present for tests
           Agreement that the instruction book is reviewed   Fig 5.10.5   Pre-test meeting e key facts
           Agreement for formal fi eld construction meeting to clearly
           de fi ne all vendor procedures from receipt of equipment on site
           to initial run in of equipment
                                                              Figures 5.10.6 to 5.10.8 define recommended test activity for
                                                            the mechanical, auxiliary equipment and performance shop
       Fig 5.10.2   Potential lost test opportunities       tests respectively.

           284
   304   305   306   307   308   309   310   311   312   313   314