Page 310 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 310

Steam Turbine Best Practices  Best Practice 5 .10


                  Per API and project requirements                    The shop test is the field baseline!
                  Confirm all components are installed                 The test report must be detailed and complete
                  Confirm all accessories are installed                Review the preliminary contents of the report before leaving the
                  Monitor progress of test, look for leaks, etc.      test floor
                  Do not accept test until all requirements are met   Obtain the actual test results
                                                                      When the final report is received, check the results obtained at
                                                                      test against the final report
              Fig 5.10.6   Mechanical test e key facts                Immediately contact the vendor if there are any differences


                                                                   Fig 5.10.10   Test report – key facts


                  Must be per API and project requirements
                  Confirm that the test agenda is followed          Shop test checklist
                  Confirm all components are installed
                                                                   1. Scope
                  Confirm that all required instruments are installed
                  Monitor the progress of the test – look for leaks, etc.  - Appropriate industry specs included (ANSI, API,
                  Do not accept until all requirements are met          NEMA, etc.)
                                                                     - In-house and/or E&C specs included
                                                                     - Project specific requirements
              Fig 5.10.7   Auxiliary system test e key facts
                                                                        , Performance test  , All rotors  , One rotor
                                                                        , Test (equivalent) conditions
                                                                        , Field (actual) conditions
                                                                        , Mechanical test  , All rotors  , One rotor
                                                                        , Test (equivalent) conditions
                  Confirm mechanical test acceptance
                  Confirm auxiliary system test acceptance               , Field (actual) conditions
                  Inspect components and confirm acceptance              , Unit test of all equipment (string test)
                  Agree to any corrective action in writing                , No load    , Includes auxiliary systems
                  Accept or reject test – any corrective action requires a retest!  , Full load  , Does not include auxiliary
                                                                              systems
              Fig 5.10.8   Post test – key facts                        , Use of job couplings and coupling guards
                                                                        , Testing of instrumentation, control and protection
                                                                           devices
                At the conclusion of all test activities, there is still important  , Auxiliary system test
              work to be performed. These items are defined in              , Lure oil      , Test press   , Full press
              Figure 5.10.8.                                               , Control oil   , Test press   , Full press
                What happens if the test is not successful? Approximately  , Seal oil      , Test press   , Full press
              50% of the tests that I have either run or participated in over my  , Seal gas  , Test press  , Full press
              career have not been successful in regards to one component or  , Fuel       , Test press   , Full press
              more not meeting test requirements. Possible rejected test   , Flow measurement required
              action is noted in Figure 5.10.9.                            , Time base recording of transient events required
                                                                        , Use of all special tools during test (rotor, removal,
                                                                           coupling, etc.)
                                                                        , Shop test attendance (includes assembly and
                  Immediately provide details to the project team          disassembly)
                  Confirm if field conditions can handle the abnormality     , Site reliability  , Site maintenance  , Site
                  Determine if the ‘as tested’ machine will meet all reliability
                  requirements                                                operations
                  If the decision is to reject, inform the vendor and detail the  , Review of instruction book during shop test visit
                  reasons                                                  , Test agenda requirements
                  Do not accept unrealistic delivery delays                , Mutually agreed limits for each measured
                                                                              parameter
                                                                           , Issue for approval two months prior to contract
              Fig 5.10.9   Rejected test action
                                                                              test date
                                                                   2. Pre-test meeting agenda
                Finally, do not forget the importance of test report re-  - Meet with test department prior to test to:
              quirements. The test report is a most important document that  , Confirm test agenda requirements
              represents the ‘baseline performance’ of the unit and will be  , Confirm all test parameters have mutually agreed
              a benchmark for field operation acceptability. Test report key  established limits
              facts are noted in Figure 5.10.10.                        , Review all instrument calibration procedures

                                                                                                               285
   305   306   307   308   309   310   311   312   313   314   315